ITEM : B.3. System Operations Report - Joe Perno | ||
Goals | ||
Summary | ||
ITEM OF INFORMATION: Construction Report New High School Project
Preliminary drawings have been reviewed by the State. Two comments were made and are in the process of being addressed. The Construction Manager and Architect are performing constructability reviews and material comparisons to substantiate projected budget and schedule. Project drawings are complete at 75% for Civil and 25% for architectural, structural, mechanical, electrical, and plumbing. |