ITEM : D.4. Apalachee High School ADA compliance project - Joe Perno | ||
Recommendation | ||
The Superintendent recommended approval of Grahl Construction out of Athens, Georgia, at a cost of $32,188, for ADA improvements at the Apalachee HS softball complex. SPLOST funds will be used for this project. | ||
Summary | ||
Improvements are necessary at the Apalachee HS softball complex to make reasonable accommodation for ADA access. This includes the installation of concrete walkways, ramps, and bleacher pads as well as upgrades to the restroom. | ||
Financial Impact | ||
Grahl Construction Athens, GA $32,188.00 Bowen & Watson, Inc. Toccoa, GA $38,406.00 Carroll Daniel Construction Gainesville, GA $47,218.00 |